This page tries to estimate the release date of Futunk milestones, based on the feature roadmap and outstanding issues with the underlying codebase. All dates are speculative and mostly useless except for tracking my own progress.
Kiki Framework
Bugs/Issues/Enhancements: 47
Futunk
Bugs/Issues/Enhancements: 37
Predicted effort remaining
- 84 issues at 6 average hours: 504 hours
- 27 roadmap features at 20 average hours: 540 hours
- 47 roadmap subfeatures at 4 average hours: 188 hours
- Total: 1232 hours
Adjusted feature effort including issue resolvement
- 504 issue hours for 27 features: 18.67 additional hours per feature (38.67 hours per feature)
Predicted Milestone accomplishments
- Private Beta β – Supporters: 16 September 2025
4 features → 154.67 hours
12 subfeatures → 48.00 hours
202.67 hours at 2 hours per day → 101.33 (week)days - Private Beta β – Runners: 30 January 2026
4 features → 154.67 hours
10 subfeatures → 40.00 hours
194.67 hours at 2 hours per day → 97.33 (week)days - Public Beta β: 10 August 2026
6 features → 232.00 hours
10 subfeatures → 40.00 hours
272.00 hours at 2 hours per day → 136.00 (week)days - Launch: 29 March 2027
8 features → 309.33 hours
5 subfeatures → 20.00 hours
329.33 hours at 2 hours per day → 164.67 (week)days - Post-Launch Planned Features: 12 August 2027
4 features → 154.67 hours
10 subfeatures → 40.00 hours
194.67 hours at 2 hours per day → 97.33 (week)days - User Contributed Ideas: 9 September 2027
1 features → 38.67 hours
0 subfeatures → 0.00 hours
38.67 hours at 2 hours per day → 19.33 (week)days